Liftng Operation
DraftReference: RA-2026-pwB89pB2
Total Activities
12
High Risk
3
Medium Risk
9
Low Risk
0
📄 Method Statement
No method statement was uploaded for this assessment.
Task Risk Assessment Worksheet
Project
132 kv cable works
Client
Taqa
Consultant
Green
Main Contractor
El Sewdy
Subcontractor
Heliopolis
Activity
Liftng Operation
Assessors
—
Project Manager
signature
—
HSE Engineer
signature
—
Project Manager
signature
—
Civil Engineer
signature
—
HSE Engineer
signature
Risk Assessment Matrix
| SN | Activity | Hazard | Consequence | Groups Exposed | Controls | Initial Risk | Additional Controls | Residual Risk |
|---|---|---|---|---|---|---|---|---|
| 1 | Complete HDPE Duct Infill | 1. Vehicle movement and traffic hazards 2. Manual handling during loading/unloading 3. Uneven ground conditions | Personal injury, property damage | Site Personnel, Subcontractors, Public | 1. Implement traffic management plan 2. Designated walkways 3. Mandatory PPE 4. Speed limit enforcement |
P
3
×
S
3
9
|
1. Comply with ADOSH SF CoP 27.0 2. Daily vehicle inspection 3. Toolbox talk |
P
2
×
S
2
4
|
| 2 | Site mobilization and setup of temporary | Passing high-speed public traffic and moving site vehicles | Personal injury, property damage | Site Personnel, Subcontractors, Public | Approved TTM plan, high-visibility clothing (Class 3), physical water-filled/concrete barriers, advanced warning signs, and trained flagmen. |
P
3
×
S
3
9
|
Deployment of Truck Mounted Attenuators (TMA) and enforcement of reduced speed limit zone in coordination with local traffic authorities. |
P
2
×
S
2
4
|
| 3 | Trench excavation and sub-surface ground preparation | Accidental strike on existing buried live electrical cables or gas utilities | Personal injury, property damage | Site Personnel, Subcontractors, Public | Utility mapping review, CAT & Genny cable avoidance scanning, and manual trial pits (pot-holing) prior to mechanical excavation. |
P
3
×
S
3
9
|
Mandatory Permit to Dig system, use of insulated hand tools near identified utilities, and continuous competent supervision. |
P
2
×
S
2
4
|
| 4 | Uncoiling, handling, and positioning HDPE pipe | Sudden release of stored mechanical spring energy in coiled HDPE pipe | Personal injury, property damage | Site Personnel, Subcontractors, Public | Use of specialized pipe reeler/uncoiler frame, controlled strap cutting procedures, and establishing exclusion zones. |
P
3
×
S
3
9
|
Mandatory deployment of safety restraints/bands before unstrapping and wearing high-impact resistant safety glasses and gloves. |
P
2
×
S
2
4
|
| 5 | HDPE pipe jointing via electrofusion and | High-temperature heating elements, hot molten plastic, and portable electrical generators | Personal injury, property damage | Site Personnel, Subcontractors, Public | Certified welding equipment, RCD-protected generators, heat-resistant safety gloves, and portable fire extinguishers nearby. |
P
3
×
S
3
9
|
Hot Work Permit implementation, provision of localized exhaust ventilation or respiratory protection (FFP3) in confined areas. |
P
2
×
S
2
4
|
| 6 | Entry into underground chambers and manholes | Hazardous atmosphere (oxygen deficiency, toxic gases like H2S/methane), engulfment, or fall from height | Personal injury, property damage | Site Personnel, Subcontractors, Public | Confined Space Entry Permit, pre-entry 4-gas atmospheric testing, forced air ventilation, and tripod rescue system with harness. |
P
3
×
S
3
9
|
Continuous multi-gas monitoring during entry, dedicated trained top-person/standby monitor, and verified emergency rescue plan. |
P
2
×
S
2
4
|
| 7 | Mechanical winch pulling of HDPE sub-ducts | High-tension winch wire snap, rotating capstans, and pinch/nip points | Personal injury, property damage | Site Personnel, Subcontractors, Public | Properly rated winching wire with calibrated weak-link swivel, emergency stop switches, and safety guards over rotating parts. |
P
3
×
S
3
9
|
Integrated load monitoring with automatic shut-off at peak tension limits and strict exclusion zones along the tension line. |
P
2
×
S
2
4
|
| 8 | Duct proving (mandrel testing) and air | Uncontrolled high-pressure compressed air release and projectile ejection of foam pig or mandrel | Personal injury, property damage | Site Personnel, Subcontractors, Public | Calibrated pressure relief valves, secure containment/catcher cage at receiving duct end, clear exclusion zone enforcement. |
P
3
×
S
3
9
|
Mandatory Pressure Testing Permit, full-face protection shields for operators, and calibrated double-gauge manifolds. |
P
2
×
S
2
4
|
| 9 | Positioning mobile crane near live overhead power lines and substation yards | Proximity to high-voltage energized overhead conductors and electro-magnetic induction zones | Electrocution, high-voltage arcing, fatal electric shock, catastrophic fire, equipment damage, grid tripping | Crane operator, riggers, banksman, ground personnel | Establish minimum approach distances (MAD) per voltage level, deploy dedicated Banksman, implement earthing of crane chassis, verify electrical isolation where possible |
P
4
×
S
5
20
|
Issue formal Permit to Work (PTW) and Electrical Isolation Certificate; install physical height limiting Goal Posts and proximity alarms on crane boom; use non-conductive synthetic taglines. |
P
1
×
S
4
4
|
| 10 | Rigging and slinging heavy oil-filled power transformers | Incorrect rigging configuration, dynamic center-of-gravity (CoG) shift due to internal oil, defective lifting gear | Dropped load, structural crushing fatalities, major oil spill, loss of primary electrical assets | Rigging team, lifting supervisor, nearby electrical installers | Pre-use inspection of Third-Party Certified (TPI) slings and shackles, verify transformer weight and CoG from manufacturer drawing, color-code lifting equipment |
P
3
×
S
5
15
|
Appointed Person (AP) to review and approve engineered Lifting Plan; conduct NDT on transformer integrated lifting lugs; utilize certified spreader beams to avoid tank body crushing. |
P
1
×
S
3
3
|
| 11 | Lowering switchgear panels through building floor openings into elevated electrical rooms | Uncontrolled load swing, pinch points against structural openings, restricted visibility | Crushing injuries, limb amputation, structural damage to building/equipment, internal damage to sensitive vacuum circuit breakers | Substation installation crew, riggers, signalman | Rigid barricading of exclusion zone beneath opening, taglines used to steer load, qualified signalman maintaining continuous line-of-sight |
P
4
×
S
4
16
|
Enforce strict 'Red Zone' zero-entry beneath elevated loads; install custom guide rails/skids at hatch edge; utilize radio communications between signalman and winch/crane operator. |
P
1
×
S
2
2
|
| 12 | Offloading heavy high-voltage cable drums using mobile crane | Dislodging of cable drum spindle bar, asymmetric weight distribution, rolling of drum post-landing | Load shift during lift, crane boom side-loading, impact injuries to ground handlers, cable damage | Crane operator, riggers, cable jointing technicians | Use TPI-certified cable drum spreader beam and rated spindle axle, inspect drum wooden/steel flanges for defects prior to lift |
P
3
×
S
4
12
|
Install safety locking collars/pins on spindle bar; pre-position wheel chocks on landing area before touchdown; maintain clear escape routes for ground crew. |
P
1
×
S
2
2
|
Likelihood / Frequency
| Descriptor | Likely Frequency | Probability |
|---|---|---|
| Frequent | Occurs frequently | 5 |
| Often | Occurs several times per year | 4 |
| Likely | Has occurred more than once | 3 |
| Possible | Has occurred | 2 |
| Rare | Never occurred | 1 |
Risk Matrix — Probability × Consequence
| Probability | Consequence | ||||
|---|---|---|---|---|---|
| Insignificant (1) | Minor (2) | Moderate (3) | Major (4) | Catastrophic (5) | |
| Rare (1) | 1 | 2 | 3 | 4 | 5 |
| Possible (2) | 2 | 4 | 6 | 8 | 10 |
| Likely (3) | 3 | 6 | 9 | 12 | 15 |
| Often (4) | 4 | 8 | 12 | 16 | 20 |
| Frequent / Almost Certain (5) | 5 | 10 | 15 | 20 | 25 |
| 15 – 25 | Extreme Risk | Activity or industry should not proceed in current form. |
| 8 – 12 | High Risk | Activity or industry should be modified to include remedial planning and action and be subject to detailed EHS assessment. |
| 4 – 6 | Moderate Risk | Activity or industry can operate subject to management and/or modification. |
| 1 – 3 | Low Risk | No action required, unless escalation of risk is possible. |